Scheduler preview not handling daylight savings time correctly

Description

I'm trying to configure a replication task to start every wednesday at 12:05 AM. The schedule preview seems like the next task for next Wednesday, but after that on Tuesdays at 11:05PM. Am I doing this wrong?

Problem/Justification

None

Impact

None

SmartDraw Connector

Katalon Manual Tests (BETA)

Activity

Show:

Bug Clerk April 14, 2021 at 7:25 AM

Mike Gittelman April 10, 2021 at 10:17 PM

 I think you are correct about the PST to PDT change causing the issue.  I'm no longer seeing the problem after the change over.

Shouldn't it remain the same instead of compensating for the time difference?  In other words, if I schedule it at 1AM before the time switchover, it should show as 1AM afterwards, not 12AM, since when it runs after the switch, it will still run at 1AM.

Denys Butenko April 8, 2021 at 10:58 AM

Fix preview:

Bug Clerk April 8, 2021 at 10:39 AM

Denys Butenko April 7, 2021 at 12:03 PM

I wasn't able to reproduce the issue on 12.0-U2 and freshly installed 12.0-U2.1.
Is it possible the issue was caused by time changes PST → PDT?

Complete

Details

Assignee

Reporter

Labels

Components

Affects versions

Priority

More fields

Katalon Platform

Created March 3, 2021 at 9:38 PM
Updated July 1, 2022 at 5:13 PM
Resolved April 26, 2021 at 8:18 AM